Srinagar Power Shutdown on October 6, 7 and 12: Check Affected Areas and Timings

Srinagar Power Shutdown on October 6, 7 and 12: Check Affected Areas and Timings

SRINAGAR: Power supply in several areas of Srinagar and its outskirts will remain affected on October 6, October 7 and October 12, 2026, due to scheduled shutdowns of multiple 33 kV power transmission lines.

According to the shutdown schedule issued by the Chief Engineer, Distribution, Kashmir Power Distribution Corporation Limited (KPDCL), the outages have been planned to facilitate maintenance-related work on the respective power lines.

Residents in the affected areas have been advised to plan accordingly during the scheduled shutdown hours.

Power Shutdown in Srinagar on October 6

On October 6, power supply in several areas will be affected due to the shutdown of the 33 kV Alusteng-Zakoora feeder and 33 kV Alusteng-Nagbal line.

The scheduled shutdown will remain in effect from 12 noon to 2 pm.

Areas affected include:

  • Pandach
  • Pathan Colony
  • Gulabagh
  • Mir Mohalla
  • Umarhair
  • Nowbugh
  • Ahmad Nagar
  • 90 Feet Road
  • Khalmullah
  • Shuhama
  • Bakura
  • Darend
  • Nagbal
  • Fatehpora
  • Gadoora
  • Tulbagh
  • Chunduna
  • Saloora
  • Shairpathri
  • Adjoining areas

Wanganpora-Khanyar-Rainawari line shutdown

Power supply to Kondabal, Hassanabad, Hazaribagh, JLNM Hospital, Jogilanker, Maqdoom Sahib, Miskeen Bagh and Rozbal, along with adjoining areas, will also be affected.

The 33 kV Wanganpora-Khanyar-Rainawari line will remain shut from 8 am to 2 pm on October 6 and October 12.

Power Shutdown on October 7

On October 7, the scheduled shutdown of the 33 kV Airforce line will affect power supply from 10 am to 3 pm.

Affected areas include:

  • Peerbagh
  • Cooperative Colony
  • Jeelanabad
  • Hyderpora
  • Nadru
  • PHQ
  • Airport
  • Sheikhpora
  • Friends Colony
  • Humhama Heights
  • Tawheed Bagh
  • Adjoining areas

Cheshmashahi-TRC-Nedous Line Shutdown

Another scheduled shutdown on October 7 will affect power supply from 11 am to 2 pm due to maintenance work on the 33 kV Cheshmashahi-TRC-Nedous line.

The affected locations and connections include:

  • Chief Minister’s residence
  • Deputy Chief Minister’s residence
  • Paras Hospital
  • 11 kV F4 Sonwar line

Srinagar Power Supply Maintenance Schedule

The shutdowns have been scheduled by KPDCL as part of maintenance-related work on the respective power lines.

Residents and businesses in the listed areas should take note of the scheduled timings and make necessary arrangements in advance.

Srinagar Power Shutdown Schedule at a Glance

DateTimePower LineMain Affected Areas
October 612 noon–2 pm33 kV Alusteng-Zakoora & Alusteng-NagbalPandach, Gulabagh, Ahmad Nagar, 90 Feet Road, Shuhama and others
October 6 & 128 am–2 pm33 kV Wanganpora-Khanyar-RainawariKondabal, Hassanabad, Hazaribagh, JLNM Hospital, Rozbal and others
October 710 am–3 pm33 kV Airforce linePeerbagh, Hyderpora, Airport, Humhama Heights and others
October 711 am–2 pm33 kV Cheshmashahi-TRC-NedousCM residence, Deputy CM residence, Paras Hospital, F4 Sonwar

Residents in Srinagar and adjoining areas are advised to check whether their locality falls under the scheduled shutdown areas before the specified outage timings.