JK Power Shutdown Schedule: Outage Announced for August 29 and September 1
Srinagar: The Jammu and Kashmir Power Distribution Corporation Limited (KPDCL) has announced a scheduled power shutdown in parts of Srinagar under the Rawalpora receiving station.
The power shutdown notice was issued on August 27, 2026, and the affected areas will experience a temporary power outage on August 29 and September 1, 2026.
JK Power Shutdown Schedule
According to the KPDCL notice, the shutdown will affect consumers supplied through 11 kV Feeders F#03 and F#04 from the Rawalpora receiving station.
| Details | Information |
|---|---|
| Receiving Station | Rawalpora |
| 11 kV Feeder | F#03 & F#04 |
| Shutdown Dates | August 29, 2026 & September 1, 2026 |
| Power Shutdown Time | 8:00 AM to 2:00 PM |
| Load to Remain Off | 3 MW |
| Affected Areas | Mujib Bagh, Baghe Hyder and Hydropera |
Areas to Face Power Outage
The scheduled power shutdown will affect the following areas:
- Mujib Bagh
- Baghe Hyder
- Hydropera
Power supply in these areas is scheduled to remain affected from 8:00 AM to 2:00 PM on the dates mentioned in the notice.
Important Date Clarification
The notice is dated August 27, 2026. Although this update is being published on August 28, the shutdown dates mentioned by KPDCL are August 29, 2026, and September 1, 2026. No August 28 shutdown is mentioned in the notice shown above.
Consumers in the affected areas are advised to plan accordingly and keep essential electrical and battery-operated devices charged before the scheduled outage.
KPDCL has expressed regret for the inconvenience caused due to the planned shutdown.
KPDCL Helpline
For power-related complaints or assistance, consumers can contact the KPDCL helpline:
1800 1807 666
6006613056-60
JK Power Shutdown Schedule – Key Details
The JK Power Shutdown Schedule for the Rawalpora area covers a six-hour planned outage from 8 AM to 2 PM on August 29 and September 1. The shutdown is associated with 11 kV Feeders F#03 and F#04, with approximately 3 MW of load scheduled to remain off.
Residents and businesses in Mujib Bagh, Baghe Hyder and Hydropera should take necessary precautions during the scheduled power inte