JKPTCL Announces 14-Day Transformer Shutdown from Nov 18

JKPTCL Orders 14-Day Transformer Shutdown in Kishtwar for Major Capacity Upgrade

SRINAGAR: The Jammu Kashmir Power Transmission Corporation Limited (JKPTCL) has announced a 14-day shutdown of a 20 MVA transformer at the 2×20 MVA, 132/33kV Grid Substation in Kishtwar Katarsoma, scheduled from November 18 to December 1, 2025,
The shutdown has been planned to enhance the station’s overall load capacity from the existing 40 MVA to 70 MVA, allowing smoother and more reliable power supply in the long run.

For more updates on Jammu and regional developments, visit our Jammu News section — https://www.timesofkashmir.in/jammu-news-latest-breaking-news-updates-today-times-of-kashmir/
Follow our WhatsApp Channel for instant updates — Join Now

During the upgrade period, power supply is expected to be reduced by nearly 10 MW. JKPTCL officials said rotational load shedding will be implemented across 33kV and 11kV feeders to balance the temporary shortfall.
Areas expected to face intermittent disruptions include Mandal, Iqhala, Padyarna, Padar, Dangdoru, Hatta, Dedpath, Sarthal, and Malipath.

Authorities have urged consumers to plan their electricity usage during the shutdown period and assured that the ongoing capacity augmentation will significantly improve reliability and efficiency once completed.